Location: Lake Oswego, Oregon
Home Size: 3,000 sq ft
Roof Type: Architectural asphalt shingle
Roof Complexity: Moderate to high (multiple valleys, skylights, steep rear pitch)
Timeline: 5 weeks from estimate to completion
Investment: Approximately $28,400
The Situation
When Mike and Sarah purchased their Lake Oswego home nearly 18 years ago, the roof had already seen several Oregon winters. Over the last two years, they noticed growing signs that replacement was becoming unavoidable.
“We started finding granules in the gutters, a couple shingles had blown off during a windstorm, and there was a small water stain forming in one of the upstairs bedrooms,” Sarah explained.
Like many Portland-area homeowners, they delayed replacing the roof because they worried about cost and disruption.
“We kept hoping we could squeeze one more year out of it,” Mike said.
However, after a heavy rainstorm in early September and a contractor inspection showing deteriorating flashing and soft decking around one skylight, they decided it was time to move forward before winter.
The Estimate Process
The homeowners gathered four roofing estimates, ranging from $18,900 to $36,000.
At first glance, the lowest bid looked appealing. But after comparing scopes of work, they realized not all proposals included the same materials or protection.
The biggest differences included:
- Type of underlayment used
- Ventilation improvements
- Flashing replacement around skylights and chimney
- Cleanup process and nail protection
- Warranty coverage
- Whether plywood replacement was included or extra
The chosen contractor was not the cheapest or most expensive.

“We felt the middle-priced company explained everything clearly and gave us confidence they were planning for Oregon weather, not just installing shingles,” Mike said.
What the Roof Replacement Included
The project scope included:
1.) Full tear-off of existing shingles
2.) Hybrid underlayment
3.) Ice and water shield in vulnerable areas
4.) Architectural shingles rated for high wind resistance
5.) New flashing around skylights and chimney
6.) Ridge ventilation improvements for attic airflow
7.) Replace six damaged plywood sheets discovered at tear-off
8.) Full debris cleanup and magnetic nail sweep
Contact HER Roofing Today
And Get a Free Estimate for Your Roof Replacement
Timeline: What the Homeowners Experienced
Week 1: Inspection & Planning
A full roof inspection identified weak areas around flashing and ventilation concerns. Materials and color options were reviewed.
Week 2–4: Scheduling
Because fall is a busy season for Portland roofers, installation was scheduled roughly three weeks out.
Installation Week
Day 1:
Dump trailer arrived, landscaping protection installed, and old roofing materials removed.
Day 2:
Crew discovered minor plywood rot near one skylight and replaced damaged decking before waterproofing.
Day 3–4:
New underlayment, flashing, ventilation improvements, and shingles installed.
Day 5:
Final cleanup, walkthrough, warranty review, and permit closeout.
“We were honestly surprised how fast it moved once it started,” Sarah said.
Unexpected Costs
The only surprise expense was replacing damaged roof decking after tear-off.
Additional cost: $1,350
“Luckily, they showed us photos before moving forward, so it didn’t feel like a hidden upsell,” Mike said.
Final Result
The homeowners completed the project before Oregon’s rainy season and reported:
- Better attic airflow
- Improved curb appeal
- Peace of mind heading into winter
- Increased confidence in resale value
Their biggest takeaway?
“If we could do it over, we probably would have replaced it a year earlier instead of stressing every time it rained.”
Typical Cost Range for Similar Portland Homes
For a Portland-area home around 3,000 square feet, homeowners typically spend $22,000–$35,000+ depending on:
- Roof pitch
- Complexity
- Material selection
- Ventilation upgrades
- Decking repairs
- Accessibility and labor requirements
Every home is different, but most homeowners are surprised to learn that a roof replacement usually takes less than a week once installation begins, even if scheduling takes several weeks.